Gotion prepares to commission equipment at its Kenitra battery plant

The announced timetable targets the week of 20 October, ahead of industrial ramp-up.

Le Desk and Médias24 report that a 12 October statement from Gotion Power Morocco schedules equipment commissioning in Kenitra for the week of 20 October. The cell plant buildings are reported complete. The first phase targets annual capacity of 20 GWh. This is a gradual commissioning stage, not confirmation that commercial production has already reached full capacity. Aujourd’hui Le Maroc also reported this milestone on 14 October.

At the source

Source dated · Briefing published 15 October 2026

Le Desk — 12 octobre 2026, communiqué GPM rapportéMédias24 — 12 octobre 2026Aujourd’hui Le Maroc — 14 octobre 2026